Kingsway Clinic Refresh
- Project address
- 5230 Kingsway
- Prime contract signed
- Feb 16, 2026
- Total project value
- $40,000.00
British Columbia
Pending in forceConstruction Prompt Payment Act (SBC 2025, c. 24)
BC's Construction Prompt Payment Act received Royal Assent 2025-11-27 and is not yet in force (commencement by regulation, s. 59). Tiercord retains working-model payment, notice and adjudication dates as inactive reference records, excluded from statutory overdue counts, urgency and reminders. Invoice balances and contractual duties remain separate. Applicable holdback and lien clocks come from the Builders Lien Act, which is in force.
Lien filing window closes
Met- Satisfied
- Sep 29, 2026on the deadline
- Due
- Sep 29, 2026, 11:59 p.m. PT
WorkflowsThis clock is closed on the record
This lien-filing clock is closed on this project's record. Tiercord does not record lien registrations, so this is not confirmation that a lien was registered: the land title registry is the authority on what is on title, and a registered lien runs on its own perfection deadlines.
Lien filing window closes
Liens must be filed within 45 days of substantial completion / abandonment / contract end. After that lien rights are extinguished.
- Started
- Aug 15, 2026, 12:00 a.m. PT
- Window
- 45-day window
- Statutory reference
- BC Builders Lien Act Section 20
Lien filing window closes
Met- Satisfied
- Sep 29, 2026on the deadline
- Due
- Sep 29, 2026, 11:59 p.m. PT
WorkflowsThis clock is closed on the record
This lien-filing clock is closed on this project's record. Tiercord does not record lien registrations, so this is not confirmation that a lien was registered: the land title registry is the authority on what is on title, and a registered lien runs on its own perfection deadlines.
Lien filing window closes
Liens must be filed within 45 days of substantial completion / abandonment / contract end. After that lien rights are extinguished.
- Started
- Aug 15, 2026, 12:00 a.m. PT
- Window
- 45-day window
- Statutory reference
- BC Builders Lien Act Section 20
Holdback release is past due
Overdue- Due
- Oct 9, 2026, 11:59 p.m. PT
- Recorded amount
- $4,000.00
WorkflowsThe holdback period elapsed and the funds remain unpaid to you. This is a cash-flow consequence, not a forfeiture, your right to the holdback is unaffected. Chase the upstream payer; if non-payment persists, refer the holdback amount to adjudication or register a lien within the statutory filing window.
Holdback release eligible
After the holdback period (55 days from substantial completion / certification), holdback amounts become eligible for release.
If you miss it
Funds remain held; cash flow impact only; no rights are lost.
- Responsibility
- They owe you
- Started
- Aug 15, 2026, 12:00 a.m. PT
- Window
- 55-day window
- Statutory reference
- BC Builders Lien Act Section 8
(1)- (2)
Holdback release eligible
Met late- Satisfied
- Oct 20, 202611 days late
- Due
- Oct 9, 2026, 11:59 p.m. PT
WorkflowsHoldback was released to you
The holdback was released and this clock is closed. The payment that settled it is recorded on this project. This was satisfied after the deadline had passed, so anything that had already accrued or become available by then is unaffected by the late satisfaction.
Holdback release eligible
After the holdback period (55 days from substantial completion / certification), holdback amounts become eligible for release.
- Started
- Aug 15, 2026, 12:00 a.m. PT
- Window
- 55-day window
- Statutory reference
- BC Builders Lien Act Section 8
(1)- (2)