North York Loft Conversion
- Project address
- 212 Sheppard Ave E
- Prime contract signed
- Jul 11, 2026
- Total project value
- $350,000.00
Ontario
In forceConstruction Act (R.S.O. 1990, c. C.30) in force since October 1, 2019.
Adjudication authority: Ontario Dispute Adjudication for Construction Contracts (ODACC).
Deficiency review window
MetInvoice NYL-087
- Satisfied
- Sep 14, 20265 days early
- Due
- Sep 19, 2026, 08:59 p.m. PT
WorkflowsDeficiency window is closed
This deficiency window is closed on the record. The counterparty's opportunity to flag missing invoice elements is no longer running.
Deficiency review window
A 7-day window to flag missing s. 6.1 elements on an invoice. Past this date the invoice is treated as 'proper' and the 28-day clock starts.
- Started
- Sep 12, 2026, 01:15 p.m. PT
- Window
- 7-day window
- Statutory reference
- Ont. Construction Act Section 6.1
(2)
Deficiency review window
Met lateInvoice NYL-061
- Satisfied
- Oct 1, 20265 days late
- Due
- Sep 26, 2026, 08:59 p.m. PT
WorkflowsDeficiency window is closed
This deficiency window is closed on the record. The counterparty's opportunity to flag missing invoice elements is no longer running. This was satisfied after the deadline had passed, so anything that had already accrued or become available by then is unaffected by the late satisfaction.
Deficiency review window
A 7-day window to flag missing s. 6.1 elements on an invoice. Past this date the invoice is treated as 'proper' and the 28-day clock starts.
- Started
- Sep 19, 2026, 01:15 p.m. PT
- Window
- 7-day window
- Statutory reference
- Ont. Construction Act Section 6.1
(2)
Dispute window
MetInvoice NYL-087
- Satisfied
- Sep 14, 202612 days early
- Due
- Sep 26, 2026, 08:59 p.m. PT
WorkflowsDispute window is closed
This dispute window is closed on the record. It is no longer running against your invoice, and any notice of non-payment that was served is listed on the invoice.
Dispute window
A 14-day window to formally dispute an invoice by issuing a notice of non-payment.
- Started
- Sep 12, 2026, 01:15 p.m. PT
- Window
- 14-day window
- Statutory reference
- Ont. Construction Act Section 6.4
(2)
Deficiency review window
MetInvoice NYL-101
- Satisfied
- Sep 27, 20265 days early
- Due
- Oct 2, 2026, 08:59 p.m. PT
WorkflowsDeficiency window is closed
This deficiency window is closed on the record. The counterparty's opportunity to flag missing invoice elements is no longer running.
Deficiency review window
A 7-day window to flag missing s. 6.1 elements on an invoice. Past this date the invoice is treated as 'proper' and the 28-day clock starts.
- Started
- Sep 25, 2026, 01:15 p.m. PT
- Window
- 7-day window
- Statutory reference
- Ont. Construction Act Section 6.1
(2)
Dispute window
MetInvoice NYL-061
- Satisfied
- Oct 1, 20262 days early
- Due
- Oct 3, 2026, 08:59 p.m. PT
WorkflowsDispute window is closed
This dispute window is closed on the record. It is no longer running against your invoice, and any notice of non-payment that was served is listed on the invoice.
Dispute window
A 14-day window to formally dispute an invoice by issuing a notice of non-payment.
- Started
- Sep 19, 2026, 01:15 p.m. PT
- Window
- 14-day window
- Statutory reference
- Ont. Construction Act Section 6.4
(2)
Dispute window
MetInvoice NYL-101
- Satisfied
- Sep 27, 202612 days early
- Due
- Oct 9, 2026, 08:59 p.m. PT
WorkflowsDispute window is closed
This dispute window is closed on the record. It is no longer running against your invoice, and any notice of non-payment that was served is listed on the invoice.
Dispute window
A 14-day window to formally dispute an invoice by issuing a notice of non-payment.
- Started
- Sep 25, 2026, 01:15 p.m. PT
- Window
- 14-day window
- Statutory reference
- Ont. Construction Act Section 6.4
(2)
Owner payment due
Met lateInvoice NYL-087
- Satisfied
- Oct 13, 20263 days late
- Due
- Oct 10, 2026, 08:59 p.m. PT
- Recorded amount
- $12,360.00
WorkflowsPayment received in full
This invoice was paid in full and the 28-day owner-payment clock is closed. The payment that settled it is recorded on this invoice. This was satisfied after the deadline had passed, so anything that had already accrued or become available by then is unaffected by the late satisfaction.
Owner payment due
Payment is due 28 days after a proper invoice is received, unless a notice of non-payment was issued within the dispute window.
- Started
- Sep 12, 2026, 01:15 p.m. PT
- Window
- 28-day window
- Statutory reference
- Ont. Construction Act Section 6.4
(1)
Payment is past due
OverdueInvoice NYL-061
- Due
- Oct 17, 2026, 08:59 p.m. PT
- Recorded amount
- $10,094.00
Record paymentWorkflowsThe 28-day owner-payment window expired. Statutory interest is now accruing in your favour. You can refer the unpaid amount to interim binding adjudication, and your lien rights remain available within the statutory filing window. Record the payment here when it arrives.
Owner payment due
Payment is due 28 days after a proper invoice is received, unless a notice of non-payment was issued within the dispute window.
If you miss it
Statutory interest begins accruing the day after; non-payment may trigger lien and adjudication remedies.
- Responsibility
- They owe you
- Started
- Sep 19, 2026, 01:15 p.m. PT
- Window
- 28-day window
- Statutory reference
- Ont. Construction Act Section 6.4
(1)
Unpaid-cascade deadline
MetInvoice NYL-087
- Satisfied
- Oct 13, 20264 days early
- Due
- Oct 17, 2026, 08:59 p.m. PT
WorkflowsSub-payment obligation is discharged
This sub-payment clock is closed on the record, either by paying your subs or by serving the notice with an undertaking to adjudicate. Nothing further is outstanding on it.
Unpaid-cascade deadline
Even if the owner hasn't paid you, you must pay your subs by day 35, or issue a notice with an undertaking to adjudicate.
- Started
- Sep 12, 2026, 01:15 p.m. PT
- Window
- 35-day window
- Statutory reference
- Ont. Construction Act Section 6.5
(4)
Adjudication materials due
MetInvoice NYL-061
- Satisfied
- Oct 20, 20261 day early
- Due
- Oct 21, 2026, 08:59 p.m. PT
- Recorded amount
- $10,094.00
WorkflowsYour materials were submitted
Your claimant materials are recorded as submitted and the materials clock is closed. The determination clock is tracked separately.
Adjudication materials due
Once an adjudicator is appointed, claimant materials must be submitted within 5 days.
- Started
- Oct 16, 2026, 09:00 a.m. PT
- Window
- 5-day window
- Statutory reference
- Ont. Construction Act Section 13.11
Owner payment due
MetInvoice NYL-101
- Satisfied
- Oct 23, 2026on the deadline
- Due
- Oct 23, 2026, 08:59 p.m. PT
- Recorded amount
- $16,480.00
WorkflowsPayment received in full
This invoice was paid in full and the 28-day owner-payment clock is closed. The payment that settled it is recorded on this invoice.
Owner payment due
Payment is due 28 days after a proper invoice is received, unless a notice of non-payment was issued within the dispute window.
- Started
- Sep 25, 2026, 01:15 p.m. PT
- Window
- 28-day window
- Statutory reference
- Ont. Construction Act Section 6.4
(1)
Pay subs even if owner hasn't paid
TodayInvoice NYL-061
- Due
- Oct 24, 2026, 08:59 p.m. PT
Issue notice with undertakingWorkflowsThis clock runs from the date the proper invoice was given to the owner. Pay your subs from your own funds by this date, or issue a notice with an undertaking to adjudicate.
Unpaid-cascade deadline
Even if the owner hasn't paid you, you must pay your subs by day 35, or issue a notice with an undertaking to adjudicate.
If you miss it
Subs gain the same statutory remedies as if you had been paid; you also lose the s. 6.5(5) shield from liability.
- Responsibility
- You owe
- Started
- Sep 19, 2026, 01:15 p.m. PT
- Window
- 35-day window
- Statutory reference
- Ont. Construction Act Section 6.5
(4)
Deficiency review window
MetInvoice NYL-104
- Satisfied
- Oct 21, 20265 days early
- Due
- Oct 26, 2026, 08:59 p.m. PT
WorkflowsDeficiency window is closed
This deficiency window is closed on the record. The counterparty's opportunity to flag missing invoice elements is no longer running.
Deficiency review window
A 7-day window to flag missing s. 6.1 elements on an invoice. Past this date the invoice is treated as 'proper' and the 28-day clock starts.
- Started
- Oct 19, 2026, 01:15 p.m. PT
- Window
- 7-day window
- Statutory reference
- Ont. Construction Act Section 6.1
(2)
Unpaid-cascade deadline
MetInvoice NYL-101
- Satisfied
- Oct 23, 20267 days early
- Due
- Oct 30, 2026, 08:59 p.m. PT
WorkflowsSub-payment obligation is discharged
This sub-payment clock is closed on the record, either by paying your subs or by serving the notice with an undertaking to adjudicate. Nothing further is outstanding on it.
Unpaid-cascade deadline
Even if the owner hasn't paid you, you must pay your subs by day 35, or issue a notice with an undertaking to adjudicate.
- Started
- Sep 25, 2026, 01:15 p.m. PT
- Window
- 35-day window
- Statutory reference
- Ont. Construction Act Section 6.5
(4)
They can still flag deficiencies
UpcomingInvoice NYL-106
- Due
- Oct 30, 2026, 08:59 p.m. PT
WorkflowsThe counterparty has 7 days from receipt to flag a deficient invoice. After that, your invoice is deemed proper.
Deficiency review window
A 7-day window to flag missing s. 6.1 elements on an invoice. Past this date the invoice is treated as 'proper' and the 28-day clock starts.
If you miss it
After 7 days of silence, the invoice is automatically treated as proper. The 28-day payment clock starts whether you've reviewed it or not.
- Responsibility
- They owe you
- Started
- Oct 23, 2026, 01:15 p.m. PT
- Window
- 7-day window
- Statutory reference
- Ont. Construction Act Section 6.1
(2)
Dispute window
MetInvoice NYL-104
- Satisfied
- Oct 21, 202612 days early
- Due
- Nov 2, 2026, 09:59 p.m. PT
WorkflowsDispute window is closed
This dispute window is closed on the record. It is no longer running against your invoice, and any notice of non-payment that was served is listed on the invoice.
Dispute window
A 14-day window to formally dispute an invoice by issuing a notice of non-payment.
- Started
- Oct 19, 2026, 01:15 p.m. PT
- Window
- 14-day window
- Statutory reference
- Ont. Construction Act Section 6.4
(2)
They can still dispute
UpcomingInvoice NYL-106
- Due
- Nov 6, 2026, 09:59 p.m. PT
WorkflowsThe counterparty has until this date to push back on your invoice. Once it passes, they lose that right.
Dispute window
A 14-day window to formally dispute an invoice by issuing a notice of non-payment.
If you miss it
Miss this and the invoice is deemed accepted. The right to dispute is lost.
- Responsibility
- They owe you
- Started
- Oct 23, 2026, 01:15 p.m. PT
- Window
- 14-day window
- Statutory reference
- Ont. Construction Act Section 6.4
(2)
Owner payment due
MetInvoice NYL-104
- Satisfied
- Oct 21, 202626 days early
- Due
- Nov 16, 2026, 09:59 p.m. PT
- Recorded amount
- $8,858.00
WorkflowsPayment received in full
This invoice was paid in full and the 28-day owner-payment clock is closed. The payment that settled it is recorded on this invoice.
Owner payment due
Payment is due 28 days after a proper invoice is received, unless a notice of non-payment was issued within the dispute window.
- Started
- Oct 19, 2026, 01:15 p.m. PT
- Window
- 28-day window
- Statutory reference
- Ont. Construction Act Section 6.4
(1)
They owe you payment
UpcomingInvoice NYL-106
- Due
- Nov 20, 2026, 09:59 p.m. PT
- Recorded amount
- $9,682.00
Record paymentWorkflowsPayment is due to you on this date. If unpaid, statutory interest accrues and adjudication is available.
Owner payment due
Payment is due 28 days after a proper invoice is received, unless a notice of non-payment was issued within the dispute window.
If you miss it
Statutory interest begins accruing the day after; non-payment may trigger lien and adjudication remedies.
- Responsibility
- They owe you
- Started
- Oct 23, 2026, 01:15 p.m. PT
- Window
- 28-day window
- Statutory reference
- Ont. Construction Act Section 6.4
(1)
Awaiting determination
UpcomingInvoice NYL-061
- Due
- Nov 20, 2026, 09:59 p.m. PT
- Recorded amount
- $10,094.00
WorkflowsThe adjudicator's determination is expected by this date. No action needed from you unless they request more.
Determination due
The adjudicator must issue their determination within 30 days of receiving the claimant's materials.
If you miss it
Process may extend with consent; otherwise the matter can be re-referred. Tracked for awareness.
- Responsibility
- Shared
- Started
- Oct 20, 2026, 09:00 p.m. PT
- Window
- 30-day window
- Statutory reference
- Ont. Construction Act Section 13.13
Unpaid-cascade deadline
MetInvoice NYL-104
- Satisfied
- Oct 21, 202633 days early
- Due
- Nov 23, 2026, 09:59 p.m. PT
WorkflowsSub-payment obligation is discharged
This sub-payment clock is closed on the record, either by paying your subs or by serving the notice with an undertaking to adjudicate. Nothing further is outstanding on it.
Unpaid-cascade deadline
Even if the owner hasn't paid you, you must pay your subs by day 35, or issue a notice with an undertaking to adjudicate.
- Started
- Oct 19, 2026, 01:15 p.m. PT
- Window
- 35-day window
- Statutory reference
- Ont. Construction Act Section 6.5
(4)
Pay subs even if owner hasn't paid
UpcomingInvoice NYL-106
- Due
- Nov 27, 2026, 09:59 p.m. PT
Issue notice with undertakingWorkflowsThis clock runs from the date the proper invoice was given to the owner. Pay your subs from your own funds by this date, or issue a notice with an undertaking to adjudicate.
Unpaid-cascade deadline
Even if the owner hasn't paid you, you must pay your subs by day 35, or issue a notice with an undertaking to adjudicate.
If you miss it
Subs gain the same statutory remedies as if you had been paid; you also lose the s. 6.5(5) shield from liability.
- Responsibility
- You owe
- Started
- Oct 23, 2026, 01:15 p.m. PT
- Window
- 35-day window
- Statutory reference
- Ont. Construction Act Section 6.5
(4)